Townhouse office vs. office building: renovation cost, time and permits

10 November, 2026

Many companies choose a townhouse office – or rent a townhouse as a bank branch or showroom – for the street frontage, their own signage and full control over working hours. Before deciding between a townhouse and space in an office building, and again when renovation starts, clients usually ask us three questions:

Planning a turnkey office fit-out?

TECO designs and builds offices turnkey: finishes, furniture from our own workshop, M&E and fire safety – handover in 25–50 days, after-sales maintenance included.

Design VND 150,000–350,000/m²; turnkey fit-out VND 2–8 million/m² depending on scope and finish level.

Call +84 911 111 929 Zalo 0911 111 929 See our office service → Furniture workshop →

  • How much will it cost? In TECO’s experience, renovating a townhouse office with structural changes – construction, MEP, air conditioning, fire protection and furniture – typically runs at VND 4.5–5 million per m² of floor area. Townhouse rent is usually lower than office-building rent, but the infrastructure a building already provides is something you have to build yourself.
  • How long will it take? 560 m² of floor area, including structural work, delivered by TECO in 35 days. That speed only works if the design is fixed early and several work packages run in parallel.
  • What permits and fire-safety approvals are needed? Interior renovation that does not touch load-bearing structure or change the building’s use is exempt from a building permit, but the works must still be registered with the local authority (commencement registration or renovation registration). Offices under 7 storeys and under 3,000 m² of floor area do not need a fire-safety design appraisal, but must still be fully equipped.

This article answers each question, based on a project TECO handed over in October 2026 and our experience on other townhouse projects.

Project summary
ProjectOCB Long Thanh bank transaction office (Dong Nai)
Existing conditionTwo adjoining 3-storey townhouses, 185 m² footprint, 560 m² total floor area
ScopeOpening up the two houses, extending the slab, adding a staircase and new toilets; new electrical, air conditioning, water supply and drainage, waterproofing, fire protection and furniture
Construction time35 days
Bank transaction hall after renovating two adjoining townhouses
The transaction office after renovation: two townhouses opened up into one continuous banking hall.

1. Townhouse office vs. office building

CriteriaTownhouseOffice building
RentUsually lower per m²Higher, plus a management fee
Existing infrastructureAlmost everything must be redone: electrical, AC, water, fire protection, waterproofingCentral AC, fire protection, lifts and toilets already in place
StructureWalls can be opened, slabs extended and stairs added if the owner agrees and safety is ensuredChanges are almost never allowed
Working hoursFlexible – mainly a matter of keeping on good terms with the neighboursSet by building management; many buildings allow night work only
Brand visibilityStreet frontage, large signageOnly a name plate in the lobby
LegalYou handle renovation registration, fire safety and the electricity contract yourselfBuilding management handles most of it; you submit drawings for approval

In short: a townhouse is cheap on rent but expensive on fit-out. Add both together and spread them over the lease term before comparing with an office building.

Townhouse facade converted into a bank transaction office
The townhouse’s biggest advantage: its own frontage and signage, with customers walking straight from the pavement to the counter.
Townhouse office work area after renovation
The work area behind the counters, laid out across the two joined houses.

2. What to check before signing a townhouse lease

Most unexpected renovation costs come from things you cannot see during a viewing. TECO always surveys these five points before a client signs:

  1. Leaks: check the two party walls shared with the neighbours and the roof – the most common leak points in old townhouses.
  2. Structure: which walls are load-bearing, and can the floor carry the new use (storage, filing cabinets, safes)?
  3. Septic tank, manholes and drainage: are they large enough for the new number of toilets and occupants?
  4. Power: the existing supply capacity, and whose name the electricity contract is in.
  5. Escape routes: do the staircase and entrance doors meet fire-safety requirements for an office?

Write into the lease exactly what may be demolished, opened up or altered, and what condition the premises must be returned to at the end. Reinstatement cost at lease end should be included in the renovation budget from the start – typically about 3% of the total.

3. Structure: joining two houses, extending the slab, adding a staircase

To create a large enough banking hall, TECO:

  • Removed the dividing wall between the two houses on the ground and first floors.
  • Extended the slab over the void area to gain usable floor space.
  • Added a new staircase and new toilets.

The structural solution was a steel frame with a cast concrete slab. The new staircase has a load-bearing steel frame with stone treads. Steel is prefabricated, quick to erect and needs little demolition of the existing building, which made the 35-day programme possible.

Programme lesson: every type of office has one “heavy” item. For a bank branch it is the vault; for other offices it may be a server room, a soundproofed meeting room or custom-made joinery. This item takes the longest, so its design must be fixed and work started first, with everything else running in parallel. Leave it until last and 35 days is almost impossible.

Demolishing the dividing wall between two townhouses
Demolishing the dividing wall between the two townhouses to join the floors.
Opening up the party wall during townhouse renovation
The dividing wall between the two houses after opening up.
Erecting a steel-framed staircase in a renovated townhouse
The load-bearing steel staircase frame during erection.
Steel staircase with stone treads in a townhouse office
The staircase after stone treads and steel balustrade were fitted.

Note: any work that touches the structure needs structural calculations and drawings and the owner’s written consent. This also determines the permit route (see section 6).

4. Waterproofing, water supply and drainage: two things often overlooked

On this project the air conditioning, water supply and drainage, and waterproofing were all completely replaced. Two problems we find in almost every old townhouse:

  • Leaks through the party walls and roof. Survey and fix them for good during the renovation. Fixing them after the interior is finished costs twice as much and damages the fit-out.
  • Old drainage. When adding toilets, check whether the existing septic tank, manholes and pipes can handle the new use. If not, they must be upgraded or replaced.
Leaking gutter and parapet of an old townhouse
Old gutters and roof parapet: common leak points to fix before interior finishing.
Checking metal roof waterproofing on an old townhouse
The old metal roof being checked and waterproofed.
Building a new toilet in a townhouse office
New toilet during tiling.
Finished toilet in an office converted from a townhouse
The new toilet after completion.

5. Electrical: more than pulling cables

This building had enough capacity, so no power upgrade was needed. But there is one step few people notice: transferring the electricity supply contract to the tenant, so the tenant pays the bills directly and receives valid VAT invoices. On this project the power company took a deposit of about VND 5 million, refunded when the contract is transferred back to the owner at lease end. Procedures and deposits vary by locality, so check with the local power company first.

If the office uses heavy equipment, a server room or high-capacity AC, check the supply capacity during the viewing. Upgrading capacity or bringing in three-phase power adds time and cost.

New main distribution board in a renovated townhouse office
New main distribution board with separate circuits for lighting, sockets and air conditioning.

Testing desk power and data outlets
Desk power and data boxes tested with a meter before handover.

6. Permits and fire safety: get them right from the start

Renovation permits

From 1 July 2026, under Construction Law No. 135/2025/QH15 (Luật Xây dựng 2025), interior repair and renovation works are exempt from a building permit provided they do not change the purpose or use of the building, do not affect the safety of the load-bearing structure, and meet fire-safety and environmental requirements. Even when exempt, the works must still be registered with the local authority – commencement registration or repair and renovation registration – before work starts.

In practice, on TECO’s townhouse renovations the contractor files the renovation registration with the ward, and ward officers carry out periodic inspections during construction. If the renovation touches load-bearing structure or changes the building’s use, ask the local construction authority beforehand whether a permit is required.

Fire protection

Under Decree 105/2025/NĐ-CP (Nghị định 105/2025/NĐ-CP, as amended by Decree 347/2026/NĐ-CP, effective 15 September 2026), there are two levels:

  • Premises under fire-safety management (Appendix I): head offices and office buildings of enterprises with 2 or more storeys or a total floor area of 100 m² or more. Most townhouse offices fall into this group: they must be fully equipped and are subject to inspection.
  • Fire-safety design appraisal required (Appendix III): buildings used as head offices or offices 7 storeys or higher, or with a total floor area of 3,000 m² or more. A typical townhouse office does not reach this threshold.

At OCB Long Thanh no appraisal was required; the fire police inspected the premises and issued an inspection record. The system comprises fire alarms, fire extinguishers and an escape staircase. For other requirements on escape routes, lighting and materials, see our article on office design standards in Vietnam.

Fire alarm control panel in a townhouse office
Fire alarm control panel next to the electrical board, with fire-fighting instructions.
Fire extinguishers and fire-safety rules in a townhouse office
Alarm bell, manual call point, extinguishers and fire-safety rules on every floor.
Escape corridor with EXIT sign in a renovated townhouse office
Escape route with EXIT signage.
Emergency light and air conditioner in a townhouse office
Emergency lighting installed alongside the new air conditioning.

7. Cost: where does the money go?

In TECO’s experience, renovating a townhouse office with structural work – construction, MEP, air conditioning, fire protection and furniture – typically comes to VND 4.5–5 million per m² of floor area. A typical cost breakdown for such a project:

ItemShareNotes
Building works (demolition, steel structure, slab, stairs, toilets, waterproofing, finishes)~42%The largest share, because of structural work and new finishes
Furniture~18%Counters, desks, cabinets, sofas (made in the TECO workshop)
Electrical (power, lighting, data)~11%All new
Industry-specific items~11%Depends on the function of each office
Air conditioning~10%All new
Fire-protection equipment~5%Alarms, extinguishers, escape
Reinstatement at lease end~3%Budget for it from day one

The key point: about a quarter of the cost (MEP, AC, fire protection) covers things an office building would mostly already have – before counting structural work and waterproofing. That is the “do-it-yourself” part of choosing a townhouse. Actual investment also depends heavily on the finish level and furniture you choose.

8. When to choose a townhouse, when to rent in an office building

Choose a townhouse whenChoose an office building when
You need frontage, signage and walk-in customers (bank branches, showrooms, training centres, clinics)Few clients visit; the space is mainly for staff
The lease is long (5 years or more), so the fit-out cost can be written offThe lease is short and you may move within 2–3 years
You need special spaces: storage, safes, a small workshop, private parkingYou need to move in fast with little upfront capital
You are in a provincial town with few good-quality office buildingsYou are in a city centre and need a professional image and good security

9. Checklist before renting a townhouse as an office

  • Have the party walls and roof been checked for leaks?
  • Does the structure allow the openings, slab changes and new stairs your layout needs? Has the owner agreed in writing?
  • Are the septic tank and manholes large enough for the new number of toilets and occupants?
  • Is the power supply sufficient? How do the electricity contract transfer and deposit work?
  • Is the renovation exempt from a building permit? Who handles commencement or renovation registration with the local authority?
  • What fire-protection systems are required? Who deals with the fire police?
  • Is the reinstatement cost at lease end in the budget?
  • Spread over the lease term, are rent plus fit-out still cheaper than an office building?
Bank transaction office completed after a 35-day townhouse renovation
The banking hall and work area after 35 days of construction.

TECO designs and builds offices and bank branches in townhouses
From site survey, structural work, waterproofing, MEP and fire protection to furniture. One point of contact, on schedule. Send TECO the address or photos of the premises and we will survey and estimate the renovation cost before you sign the lease. Call +84 911 111 929 · Email teco@tecoarch.com

Planning a turnkey office fit-out?

TECO designs and builds offices turnkey: finishes, furniture from our own workshop, M&E and fire safety – handover in 25–50 days, after-sales maintenance included.

Design VND 150,000–350,000/m²; turnkey fit-out VND 2–8 million/m² depending on scope and finish level.

Call +84 911 111 929 Zalo 0911 111 929 See our office service → Furniture workshop →

Related services: Office design & build · Bank branch design & build · Custom furniture workshop

Related projects: OCB office renovation at Hallmark · Vietbank Luong Dinh Cua transaction office

Related articles: Office renovation without closing · Office design standards in Vietnam