Renovating an operating school: how TECO organises the site

27 October, 2026

Nguyen Thanh Tam – TECO

A school needs to renovate its library or upgrade classrooms but cannot send students home. Renovating an operating school means lessons, exams and events go on, and the works have to fit in between them.

On this kind of job, small slips on site reach parents very quickly. It might be dust on a desk, drilling in the middle of a test, or a worker wandering into a classroom block.

TECO renovated the interiors of the International German School (IGS) and the Emasi Plus Waterpoint International School library while both schools kept teaching. This article explains how we organised the site on those two projects, in order from pre-construction to handing the space back. School leaders and owners can use it as a checklist of what to ask of their contractor.

Planning a school project in Vietnam?

TECO designs and builds international schools and kindergartens: joinery made in our own workshop, fire-safety (PCCC) dossiers prepared in-house, phased construction around the school year.

Design fee from VND 250,000–500,000/m², waived when TECO builds. Free site survey in Ho Chi Minh City and southern Vietnam.

Call +84 911 111 929 Zalo 0911 111 929 See our school design & build service → Furniture workshop →

Emasi Plus Waterpoint library with floor protected by plastic sheeting during works and the reading area after completion
Emasi Plus Waterpoint International School library: floor covered with plastic sheeting throughout the works (left) and the reading area after completion (right).
Workshop-made timber panels wrapped in plastic awaiting installation and a finished specialist classroom at IGS
International German School (IGS) interiors: timber panels pre-made in the workshop, wrapped and stacked on tarpaulin ready to install (left), and a specialist classroom after completion (right).

How an operating school differs from an empty site

For the same scope of work, building inside an operating school differs from an empty site at almost every organisational step:

CriterionEmpty siteOperating school
People in the areaConstruction crew onlyStudents, teachers and parents moving right next to the work zone
Working hoursSet by the contractor’s programmeSet by the school’s timetable, exams and events
NoiseNormal working hoursNoisy work only outside lesson time
DustClean at the end of each phaseProtect before starting, clean at the end of every day
SecuritySite guardThe school holds the list of workers entering each day
Materials, wasteStored within the siteFixed laydown point, removed along a dedicated route
ReportingWeekly or by milestoneStart of day, end of day, end of week

As a result, the productive hours each day are shorter. When building the programme, the contractor has to separate work that can happen during lessons from work that can only happen outside them.

Before starting: survey, timetable and zoning plan

Most problems on school projects in operation trace back to things not agreed before day one. Before mobilising, TECO and the school complete six items:

PreparationContentPurpose
Joint survey with the schoolWalk the whole route from the gate to the work zone. Note which classrooms share a wall, which rooms host exams, and which systems (air conditioning, fire alarm, CCTV, network) run through the work zoneKnow in advance what to protect and what to isolate
School timetableLesson times, breaks, drop-off and pick-up, exams, eventsSchedule noisy work and deliveries around these slots
Condition recordPhotograph floors, walls, ceilings and equipment in and around the work zone, signed by both sidesA clear basis at handover, no dispute over old versus new damage
Zoning planColour-coded plan of the work zone, workers’ route, toilet, laydown point, waste route and barriers. Escape routes kept clearThe school approves it once and the crew follows it
Personnel listWorkers, site manager, site engineer, and contact numbers on both sidesSecurity controls access; someone can act immediately if something happens
Site rulesUniform, no smoking, no entry to classroom areas, no photos of studentsBriefed to workers before their first day

The zoning plan should be signed off by the school. When something changes during the works (a new route, an extra zone), update the plan and send it again.

TECO engineers surveying the existing school library area before works
Site survey of the Emasi Plus Waterpoint library area before works began.
Ground floor zoning plan showing the workers' route and material laydown area for works in an operating school
Ground floor zoning plan: workers’ route from the main gate to a dedicated stairwell, with a tarpaulin-lined material laydown area outside the building, avoiding the main lobby and admin area.
Library floor zoning plan with tarpaulin walkway, workers' toilet, RCBO distribution board and demolition locations
Library floor zoning plan: striped-tarpaulin walkway, toilet assigned to workers, RCBO board for construction power, and locations for brick wall and drywall removal and floor chasing.

Zoning: routes, toilets, laydown and waste

Under the zoning plan for the Emasi Plus Waterpoint library, workers had their own route from the gate to the work area, never passing through student areas:

  1. Enter through the main gate and follow the path outside the building.
  2. Go up by a dedicated staircase, not through the main lobby. Materials go up in a lift assigned by the school, with the cabin lined and the floor protected.
  3. Follow the tarpaulin-lined corridor into the library.
ItemArrangementReason
Workers’ routeOne fixed route, lined with striped tarpaulin along its length, with tape on both sides where it borders areas in useDust and dirt do not travel on boots into student areas
ToiletA separate toilet on the same floor, assigned by the school on the planWorkers do not share toilets with students
Material laydownOutside the building, on tarpaulin, fencedDeliveries do not occupy lobbies or corridors
Construction powerFrom a dedicated board with RCBO protectionA tool fault trips only the construction board, not classroom power
Construction wasteBagged on the spot, removed at the end of the day along the workers’ routeNo waste left overnight in corridors
Signs, barriersAt every point where the workers’ route meets student areasStudents do not stray into the work zone

Delivery trucks also avoid drop-off and pick-up times. Bulky items such as timber panels, partitions and furniture arrive before lessons start or after school ends.

School corridor lined with striped tarpaulin as the workers' route, with cones marking the work zone
Striped tarpaulin runs the length of the workers’ route; the uncovered floor stays open to students and teachers. Cones mark the work zone in front of the lift lobby and materials stay on the tarpaulin.
RCBO construction power board, warning tape and signage, and bagged construction waste being taken out
RCBO-protected construction power board with cables in flexible conduit; warning tape and “Work in progress” signs at the zone boundary; bagged waste taken out at day’s end by pallet truck along the outside route.

Dust protection and protecting existing equipment

Dust is what escapes a work zone most easily. It travels three ways: gaps above ceilings and partitions, the air-conditioning ductwork, and workers’ boots. TECO protects each point before any chasing, cutting or sanding starts:

LocationProtectionIf skipped
Work zone boundaryTarpaulin enclosure from floor to ceiling, gaps above sealedDust drifts into classrooms over the top
Existing floorPlastic sheeting and tarpaulin over the whole work area, edges tapedScratched floor that must be polished or replaced at handover
Doors into teaching areasKept closed, gaps tapedDust passes through the gaps with draughts
Smoke detectorsDetector covers fitted; fire alarm zone isolated in coordination with the schoolDust triggers the detector and the whole school may have to evacuate
AC diffusersSealed with tape and plasticDust travels through ducts into rooms on the same system
Goods liftCabin walls lined with tarpaulin, cabin floor and lift lobby protectedScratched stainless steel, dirty floor in a lift students still use
Furniture and equipment still in useMoved to one corner and shrink-wrappedDust settles on shelves, sofas and electronics

TECO also keeps timber cutting on site to a minimum. Panels for IGS and Emasi were pre-made in TECO’s 1,300 m² joinery workshop and only installed on site. This sharply reduces wood dust and saw noise inside the school.

At the end of every day, workers must clean the work zone and wipe down along the boundary. The site engineer checks the outside of the boundary before leaving.

Tarpaulin enclosure sealing the work zone in a school library and a worker sealing an air-conditioning diffuser
Tarpaulin enclosure sealed up to the underside of the ductwork in the Emasi Plus Waterpoint library; a TECO worker seals an air-conditioning diffuser next to the EXIT sign.
Library furniture shrink-wrapped, goods lift cabin lined with tarpaulin and end-of-day cleaning
Library sofas shrink-wrapped before the area was enclosed; the goods lift cabin walls and floor lined; end-of-day cleaning with the area in front of the fire exit swept and materials stacked.

Working hours, noise and odours

Working hours are set by the school, and TECO receives the timetable before mobilising. When building the programme, we group the work by noise and odour so we know what can be done when:

Work groupExamplesWhen
Very noisyFloor chasing, brick wall demolition, concrete drilling, metal cuttingAfter school or at weekends
Moderately noisyDrywall removal, screw fixing, drilling thin wallsOutside lesson time, or when that floor has no classes
Odour-producingOil-based paint, PU wood lacquer, epoxy, floor and carpet adhesive, silicone, solvent-based waterproofingAfter school or at weekends, so the smell clears overnight
Quiet, low odourWater-based paint, installing pre-made furniture, cabling, cleaningDuring lessons
Deliveries, wasteReceiving goods, taking waste outAvoiding drop-off, pick-up and break times

Odour is harder to control than noise. Drilling stops the moment the drill stops, but paint and adhesive smells can linger for hours and spread through ducts to other rooms. For odour-producing work, TECO does three more things:

  1. Prefer water-based, low-odour materials where the design allows.
  2. Open windows to the outside or use extract fans pushing air out of the building, not into corridors.
  3. Keep AC diffusers in the work zone sealed throughout painting and gluing. The next morning, the engineer checks for odour before students arrive.

On exam or event days, noisy and odour-producing work stops completely, even within permitted hours. This calendar is collected from the school at the survey and updated weekly.

Evening and weekend work needs extra preparation: adequate task lighting and a list of who is staying on site for school security. A TECO site engineer supervises every shift.

With the work split this way, the site keeps running with quiet tasks during lessons instead of piling everything into the evenings.

Drywall and mineral wool insulation being removed after school hours inside a tarpaulin enclosure
Drywall and acoustic mineral wool removal done after school hours inside the blue tarpaulin enclosure. Debris goes straight onto tarpaulin for bagging.

Safety, security and fire protection while students are on site

In an operating school, risk is not limited to workers. Curious students may walk into the work zone. An escape route blocked by materials could have serious consequences in an emergency. TECO controls four groups:

GroupWhat TECO does
SecuritySchool security receives the worker list every morning and checks it at the gate. Workers wear TECO shirts and ID badges and stay on the approved route. New workers are briefed on site rules before entering
Escape routesNo materials, waste or scaffolding blocking fire exits, stairs, EXIT signs or the school’s fire cabinets
Fire alarmIsolate only the work-zone alarm area during working hours, informing the school before and after. Restore it and remove detector covers at the end of the day
Occupational safetyFire extinguishers in the work zone. Harness and helmet for work at height. Scaffold wheels locked. All tools plugged into the RCBO board. A safety briefing by the site engineer at the start of each shift

At the end of each shift, the engineer walks the site before leaving:

  • Switch off the construction power board
  • Lock machines and hand tools away
  • Move paint, solvents and gas cylinders away from classroom areas
  • Check barriers, signs and warning tape are still in place
  • Confirm to the school that the fire alarm has been restored

When students arrive the next morning, nothing dangerous is left within reach in the work zone. For the building’s fire protection systems themselves, see Fire Protection Installation, Acceptance and Maintenance.

School security checking workers at the gate, a toolbox talk at shift start and fire extinguishers in the work zone
Each morning school security checks workers at the gate against TECO’s list. The site engineer briefs the crew and runs a safety reminder before the shift. Extinguishers sit in the work zone and access to the school’s fire cabinet stays clear.

Daily reporting to the school

An operating school needs to know who is on campus today, what they are doing and where. TECO’s site engineer reports at three points:

WhenChannelContentHow the recipient uses it
Start of dayProject Zalo groupHeadcount by crew, list of people entering, planned work and locationsSecurity checks at the gate. The school knows in advance where workers are and which tasks are noisy or smelly
End of dayProject Zalo groupPhotos of completed work, open issues, plan for tomorrowThe school flags early if tomorrow has an exam or event that needs noisy work to stop
End of weekEmailActual quantities against programme, variations, plan for next weekSchool leaders and the owner follow progress without visiting the site

Every report includes site photos. Recipients who are not in construction can see where the work stands at a glance.

Daily report photos have two more uses:

  • When the school asks whether a scratch or damage was there before, just open that day’s photos.
  • At acceptance, concealed work such as cabling inside partitions or waterproofing under floors is already photographed day by day.
Daily construction report sent to the school via the project chat group with site photos
Daily report posted in the project chat group: headcount, work completed and the next day’s plan, with site photos.

Handling changes: working directly with end users

Operating schools usually generate more changes than empty sites, for three reasons:

  • The real users (teachers, librarians, IT staff) see the works every day and ask for adjustments.
  • School equipment such as projectors, speakers, CCTV and Wi-Fi needs agreed service positions in ceilings and walls before the ceiling is closed.
  • Demolition reveals hidden conditions such as pipes, old cabling or leaks.

TECO handles each change in six steps:

  1. The engineer photographs and records the location as soon as the issue is found or a change is requested.
  2. Update the drawings and model the option in 3D, with full dimensions and quantities.
  3. Prepare the design option with a quotation for the school to approve, stating the programme impact.
  4. Post it to the project Zalo group so the school can review it the same day.
  5. If it cannot be agreed, the site manager meets the users in person on site.
  6. Confirm the decision by Zalo message and email with a signed confirmation from the school, then update the programme.

Real case: slow shop drawing approval

On one school project, the joinery package fell behind because the shop drawings were not approved. The project manager and the users could not agree, and drawings went back and forth several times.

The users were not construction people and found it hard to picture the result from technical drawings. TECO’s site manager met them on site, walked through photos of the existing space and 3D views, and showed exactly how each option would affect daily use. The package was signed off the same day.

Lesson learned: when the decision-maker is not from the industry, the real space and 3D images get a decision faster than 2D drawings.

Detailed drawings and 3D models of library shelving updated to teachers' requests
Right after the meeting, TECO updated the layout and modelled each shelving type in 3D to the teachers’ new requests, with dimensions and quantities for the school to confirm.

Handing over zone by zone

In an operating school, TECO hands over each zone as soon as it is finished rather than waiting for the whole project. The school starts using finished zones first, and the work zone shrinks step by step.

Before returning a zone to the school, the engineer checks against a list:

ItemCheck
CleaningProfessional cleaning; remove all plastic, tarpaulin and tape with no adhesive residue on floors or walls
Fire alarmRemove detector covers, restore the alarm zone with the school and test it
AC, ventilationRemove plastic from diffusers, run the AC, check no dust remains in the diffusers
Power, lightingSwitch on all lights, test sockets, run teaching equipment at the same time
FurnitureCheck for sharp edges and stability of shelving; desks and chairs positioned as drawn
Adjacent areasCompare against the initial condition record and repair any construction damage immediately
DocumentsHandover record, list of equipment handed to the school, as-built drawings, operating instructions, warranty certificates

TECO then removes the barriers and signs from the handed-over zone and moves the workers’ route to the next zone if needed.

Emasi Plus Waterpoint library and an IGS specialist classroom after handover
Emasi Plus Waterpoint library after handover: curved glass enclosure, circular ceiling and interactive screen. Specialist classroom at IGS: white cubby shelving, glass cabinets, lab benches and ceiling-hung cable reels.

Project results

ProjectScopeSizeConditions
International German School (IGS)Interior fit-out1,200 m²School kept teaching
Emasi Plus Waterpoint International SchoolLibrary fit-out1,600 m²School kept teaching
Emasi Plus Waterpoint International SchoolBoarding block2,500 m², 2 floors, 36 unitsBuilt over the summer, with staff still working on the floor below
Group study room, classroom and attic room interiors at the International German School IGS
International German School (IGS) interiors: group study room, classroom and attic room.
Family reading area of the Emasi Plus Waterpoint library with tiered seating, mobile bookshelves and acoustic baffles
Emasi Plus Waterpoint library: family reading area with tiered seating, mobile bookshelves and suspended acoustic ceiling panels.
Boarding apartment at Emasi Plus Waterpoint after fit-out with timber flooring, doors and air conditioning
Emasi Plus Waterpoint boarding block after fit-out: timber flooring, doors, paint and air conditioning installed.

5 common mistakes when building in an operating school

  1. Not collecting the exam and event calendar, so drilling clashes with tests.
  2. Protecting only the floor, not diffusers and smoke detectors. Dust spreads through ducts to other classrooms and can set off the fire alarm.
  3. Workers sharing corridors and toilets with students because there is no zoning plan.
  4. Reporting only weekly, so the school does not know who is on campus today.
  5. Agreeing changes verbally without a record, leading to disputes at acceptance and final account.

Conclusion

Building in an operating school is harder on organisation than on technique. Most risk is shut down before day one: the school calendar, the zoning plan, the site rules. The rest comes down to daily discipline: protection, reporting, end-of-shift cleaning.

If your school needs renovation but cannot stop teaching, TECO will survey the site and propose a zoning plan from the very first visit.

Further reading: Safe design and construction of international schools: core principles · School design standards in Vietnam.

Contact TECO for a site survey: +84 911 111 929 – teco@tecoarch.com

Planning a school project in Vietnam?

TECO designs and builds international schools and kindergartens: joinery made in our own workshop, fire-safety (PCCC) dossiers prepared in-house, phased construction around the school year.

Design fee from VND 250,000–500,000/m², waived when TECO builds. Free site survey in Ho Chi Minh City and southern Vietnam.

Call +84 911 111 929 Zalo 0911 111 929 See our school design & build service → Furniture workshop →

Related services: International school & kindergarten design and build · Post-handover maintenance – TECO MSC